Guide
How to Structure a Green Hydrogen or Ammonia Project Company
The short answer
No single UAE regulator licenses "a hydrogen company". The Ministry of Industry and Advanced Technology (MoIAT) keeps the industrial registry, the Ministry of Climate Change and Environment (MoCCAE) holds the environmental remit, the Ministry of Energy and Infrastructure (MoEI) holds the energy and infrastructure remit, and the Executive Office for Control and Non-Proliferation controls the import and export of dual-use chemicals. Which of them touches a given entity depends on what that entity physically does. The question that usually decides the route is whether the company produces or converts the molecule, or only develops, supplies equipment or sells a permitted project on.
Who decides, and at which point in the chain
Think of the project as a chain: renewable power, water, electrolysis, optional conversion to ammonia, storage, port, buyer. Different authorities sit at different links. Nothing on the official sites collapses them into one permit.
MoIAT runs the Industrial Registry, a digital platform on which companies register their information annually. Registration is under Federal Decree-Law No. 25 of 2022 and its executive regulations, 79/2023. For a producer or converter, industrial registration is therefore a live topic from the start. A developer holding only land rights and contracts has a weaker claim to being an industrial establishment at all. For site safety duties and incident reporting to MOHRE, see the Amur Gas complex fire note.
MoEI's remit covers energy and infrastructure, with maritime transport and petroleum products trading among its service categories. It publishes a UAE Energy Strategy 2050 page. MoCCAE holds the environmental and climate remit. Confirm directly with MoCCAE and the emirate's environmental authority what assessment your site and process trigger, because that depends on location and scale.
None of these sites sets out a "hydrogen licence". Treat any adviser who offers one as selling a label. The practical route is a list of approvals by entity and by link in the chain, confirmed with each authority before applications start.
Ammonia, chemicals and export controls
Green ammonia brings a second regime. The Executive Office for Control and Non-Proliferation states that strategic goods and dual-use chemicals are subject to import and export control, and it runs online services for chemical goods and strategic goods. It also publishes the UAE Control List.
Check the list against three things: the finished product, intermediates, and any reagent or catalyst the plant imports. A project that exports ammonia to a European buyer and imports process chemicals touches the regime in both directions. Whether a given item needs a permit depends on the list, so read the current version before the offtake term sheet fixes a shipping date.
This is also where a technology supplier differs from a producer. A company that sells electrolyser equipment and integration work may never handle a controlled chemical. A company that moves ammonia through a port will.
The entity stack and what each company holds
Lenders in this sector expect a stack, not a single company. A development company carries early spend, studies and permits. Each production or conversion asset sits in its own project company with its own financing. Supply and operations entities sit at the edges. The point of the separation is that a failure at one seam, such as a late grid connection or a water shortfall, does not contaminate every other contract.
Each entity must be able to sign what it holds. The producer answers for the process and its safety case. The power and water suppliers deliver at the contracted profile. The exporter satisfies port, transport and certification demands. A holding company or technology vehicle belongs in the stack only if it has a real function.
Jurisdiction comes after this. Whether an entity sits on the mainland or in a zone follows its site and its customers, which is why mainland and free-zone routes are compared per entity, not once for the project. Industrial and port-adjacent zones exist for process and export plant, and the plant goes where power, water, land and the export route physically meet. A mainland company suits entities that contract with local counterparties directly. A developer weighing a storage asset beside the electrolyser faces the same seam problem as a battery-energy-storage company.
What lenders and offtakers actually test
Lenders and offtakers underwrite the interfaces. Prepare these before any bank or buyer meeting:
- An integrated mass-and-energy model that ties power and water in to product out.
- The site, utility and logistics route, with named counterparties.
- Technology and construction contracts, and who carries interface risk between them.
- The offtake and certification plan, including what the buyer's specification and green claim require.
- Financing terms and the allocation of safety and delay risk.
Certification deserves its own line. A "green" claim is only as good as the certifier's willingness to support it, and buyers often write that into the offtake. Settle the certification route before using the word in marketing or term sheets.
On the banking side, a project company with a clean file is easier to onboard: a business plan that closes the loop, ownership traced to the people behind it, and a clear account of where equity and debt come from. Velarozone's work on corporate bank account readiness and business plans and documentation covers that file. A complete file earns serious diligence. It guarantees no account, financing or approval.
Where these projects go wrong
- Forming the project company before land and utilities are credible. The entity then exists with nothing to hold, and its constitutional documents are rewritten after the first utility term sheet.
- Using "green" without a certification route. The offtaker reads the claim as a contract term.
- Ignoring water and port constraints. Both are physical, and neither bends to a corporate structure.
- Leaving interface risk between power and process assets. Each contract looks fine alone. Together they leave a gap that someone must price.
- Building the stack cheaply, then rebuilding it in diligence. Every supply, land and offtake contract is renegotiated to follow the entities into their new shape.
Budget accordingly. Entity formation is a small line inside the development budget, and the development budget is small inside the build. Velarozone's own fee depends on the route and is itemised in the engagement letter, as set out in how Velarozone works. Third-party approval fees and all plant costs come from the authorities and contractors concerned, so confirm them before filing.
From licence to operating
Because the Industrial Registry asks companies to register their information annually, that task sits in the calendar of every producing entity. People follow the plant: process-safety, engineering and project leadership credible to lenders, plus the residence visas behind them. Where owners are funds, state-linked investors or layered holding companies, the ownership file takes longer than the formation. Velarozone's regulated and complex ownership work covers that file.